STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Wehr Schneller Graben, Hannover
Auftraggeber: Landeshauptstadt Hannover, Fachbereich Tiefbau
Seit 2017
Erstellung der Entwurfs- und Ausschreibungsunterlagen für die Sanierung der Maschinentechnik, des Stahlwasserbaus und der Steganlage -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Nesserland lock in Emden
2010
Checking the documents (lock gate) of the technical components, mechanical engineering, hydraulic, electric engineering2011
Consulting (cut surface interaction between maintenance group), modification of the final planning documents and supporting at site supervision. -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Obertorwechsel der Schleuse Hausen, Main-Donau-Kanal
Auftraggeber: Wasser- und Schifffahrtsamt Nürnberg
2016
Bauüberwachung des Stahlwasserbaus und Maschinenbaus im 3-Schicht-Betrieb (Arbeiten gemäß TRGS) -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Schleuse Borssum
Auftraggeber: Niedersachsen Ports GmbH & Co
2016
Überprüfung der Technischen Ausrüstung (elektrotechnische Anlagen) im Rahmen der Bauwerkshauptprüfung -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Boat lift Niederfinow
2010-2011
Consulting, calculation and design of the sealing frame
2012
Detailed designMechanical engineering: mechanical components and statical analysis of the trough structure longitudinal guiding
-
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Ship lift Rothensee
2010 and 2016
Structure work inspection of steel construction and steel construction for hydraulic engineering for ship lifting and gathering of damage via software WSVPruf -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Water-retaining structure Greifswald
2009
Checking the mechanical engineering
2011
Checking the detailed design and the factory planning (documents), the mechanical and hydraulic components
-
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Sieltore Oldersum-Borssum
Auftraggeber: Niedersächsischer Landesbetrieb für Wasserwirtschaft, Küsten- und Naturschutz
2015
Überprüfung der Technischen Ausrüstung (maschinen- und elektrotechnische Anlagen) im Rahmen der Bauwerkshauptprüfung -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Hubtore Schleuse Geesthacht
Auftraggeber: Wasser- und Schifffahrtsamt Lauenburg
Seit 2014
Begutachtung der Schäden, Schadensbeschreibung und Ermittlung von Schadensursachen, Bewertung der Unterlagen/Konstruktion und Gutachten -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Ems-Sperrwerk
Auftraggeber: Niedersächsischer Landesbetrieb für Wasserwirtschaft, Küsten- und Naturschutz
2015
Überprüfung der Technischen Ausrüstung (maschinen- und elektrotechnische Anlagen) im Rahmen der Bauwerkshauptprüfung -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Pump station Niegripp
2010-2011
Structural inspection of steel and steel hydraulic constructions
2012
Compilation of the structural inspection file
-
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Reiherstieg Lock Hamburg reconstruction
2013-2014
Basic evaluation for the steel construction for hydraulic engineering and the technical components, preliminary planning is in progress
-
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Weser lock Dörverden
2011-2012
Consulting and checking the mechanical components (analysis of the electric lift cylinder and cable for absorbing the shock) -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Lock Uelzen II
2012
Expert monitoring during removal and fitting the water gate bearing connection -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Lock in Sülfeld near Wolfsburg
2011-2012
Analysis of the seal of the water gate, wall bearing connection, rotary segment and statement on the wall connection leakage, exchange of the economizing basin closing and water gate torsional wave, survey of bearing the axial canal closing, report -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Leda Jümme organization, weir flap Holter-Hammrich
2010
Design engine -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Trough bridge Ilmenau Nnorth and South at ESK near Bad Bevensen
2009-2010
Checking of existing documents, inspection of steel construction for hydraulics and bridge bearing, gathering of damage via software WSVPruf -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Oderdeich restoration at the Ziltendorfer marsh
2008-2010
Object supervision and checking of machinery and technical components at tidal outlet Brieskow-Finkenheerd and stop motion weir Pottack-Komplex -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Alternate reconstruction clevis weir Lindenau
2008-2010
Manufacturing supervision and checking of machinery and technical components -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Weir Neumühl in the river Schwarzen Elster
2008-2010
Execution, steel construction for hydraulic engineering and technical components, object supervision and checking2003-2004
Design concept, steel construction for hydraulic engineering and technical components -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Pottack Complex, stop motion weir Oderdeich
2008-2009
Check, dry- and wet approval of the flood barrage, check and factory supervision of the mechanical engineering -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Alternate reconstruction Neiße weir Forst
2007
Controlling and checking of technical equipment -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Alternate reconstruction weir 111, Lübbenau
2007
Controlling and checking of technical equipment -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Weir Ortrand
2007
Checking, object supervision and certification -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Big Spree weir, Cottbus
2007
Checking, object supervision and certification -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Weir Herzberg
2007
Checking, object supervision and certification -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Weir and watergate 37
2007
Checking, object supervision and certification -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Weir 29
2007
Checking, controlling and certification -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Weir and watergate 23
2007
Checking, object supervision and certification -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Weir plant and watergate Kossenblatt
2005
Design concept, steel construction for hydraulic engineering and technical components -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Weir plant Bad Liebenwerda
2003-2004
Checking and certification of the technical components -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Weir 47 near Leipe in Spreewald
2002
Checking and certification of the technical equipment -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Weir plant Märkisch Buchholz
2002
Checking and certification of the technical components -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Weir 123 near Ragow in Spreewald
2002
Checking and certification of the technical components -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
New watergate Lübben
2001-2002
Checking and certification of the technical components -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Weir plant Prieros
2001-2002
Checking and certification of the technical components -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Weir plant Kiekebusch
2001-2002
Checking and certification of the technical components -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
City watergate Eisenhüttenstadt
2000-2001
Statical and technical check of the wedge roller gate -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Weir and watergate Spremberg
2000
Checking and certification of the technical components -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Watergate Lehnitz
1997-1998
Design concept, tendering for overhaul -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Flood barrage and bridge Pechteich
1997-1998
Complete planning, tendering -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Weir plant Beeskow
1996-1998
Design concept, tendering of steel construction for hydraulic engineering and technical components -
STEEL CONSTRUCTION FOR HYDRAULIC ENGINEERING
Weir plant Beihingen
1997
Development, planning including supporting of structural framework of emergency gates